Barcoo Shire Council Reconstruction Works

Project

Barcoo Shire Council Reconstruction Works

Client

Barcoo Shire Council

Location

Jundah, QLD

Expertise

  • Road Infrastructure

Value

$3,450,000

Completion

September 2021

Project Scope

Gulf Civil were successful in the tender for the Barcoo FD1 package for the Barcoo Shire Council.

Going above and beyond to meet this deadline was a great success to the Gulf team and for a new Client.

The following project scope involve significant roadworks with complex staging considerations with works including:

The project works consisted of the following:

  • 270km of Roadworks Restoration
  • Heavy Formation, Medium Formation and Gravel Re-sheet construction
  • Bulk Excavation of silted areas
  • Bulk Fill of rutted or significantly damaged sections of road
  • Win, Load and Cart over 100,000t of Gravel
  • Construction of Floodways
  • Demolition and Construction of Bridge Replacement
  • Application of 2 coat seal
  • Use of full mobile camp for entire 3 crews utilized on the project

Project Challenges

Key challenges in the delivery of this project included:

  • Very remote working conditions with several sites being up to 220km from the local township.
  • Water sources very limited due to drought conditions within the community. Innovations required at every site to produce water cost-effectively.
  • Side-track installations required at all sites to maintain access for road trains delivering gravel. Regular maintenance and grading required over project duration.
  • Programming of works to commence the project on a limited timeframe whilst also engaging, securing, and transporting imported gravel critical to critical path sections of the project.
  • Maintaining a strong working relationship with local community stakeholders.
  • Traffic Staging and Management to always maintain 2 lanes of traffic, within a minimal width road reserve
  • Management of Cultural Heritage considerations and expectations
  • Construction within a Funding timeline for the Funding body (QRA)
  • Plant maintenance in testing conditions.
  • Adequate use of variable borrow material available to the Contractor

Highlights & Outcomes

  • Delivering the project within a Funding deadline for the Client
  • Meeting the deadline after suffering 59 days of Inclement weather impact
  • The only Contractor in the region to complete the scope of works within the Funding Deadline limitations out of several packages within the region